Data Augmentation Approaches for Estimating Curtain Wall Construction Duration in High-Rise Building...
Data Augmentation Approaches for Estimating Curtain Wall Construction Duration in High-Rise Buildings
About this item
Full title
Author / Creator
Publisher
Basel: MDPI AG
Journal title
Language
English
Formats
Publication information
Publisher
Basel: MDPI AG
Subjects
More information
Scope and Contents
Contents
Reliable project management during planning stages of a building project is a meticulous process typically requiring sufficient precedencies. Typical construction duration estimation is based on previous cases of similar projects used to validate construction duration proposals from contractors, plan overall project duration, and set a standard for...
Alternative Titles
Full title
Data Augmentation Approaches for Estimating Curtain Wall Construction Duration in High-Rise Buildings
Authors, Artists and Contributors
Author / Creator
Identifiers
Primary Identifiers
Record Identifier
TN_cdi_doaj_primary_oai_doaj_org_article_76c15c28db7e4bd59cff6608b5b93bb4
Permalink
https://devfeature-collection.sl.nsw.gov.au/record/TN_cdi_doaj_primary_oai_doaj_org_article_76c15c28db7e4bd59cff6608b5b93bb4
Other Identifiers
ISSN
2075-5309
E-ISSN
2075-5309
DOI
10.3390/buildings15040583